Home » KenGen’s Geothermal Power Plants
Business

KenGen’s Geothermal Power Plants

KenGen’s Geothermal Power Plants

KenGen owns five geothermal power stations; Olkaria I, Olkaria II, Olkaria IV, Olkaria I unit 4 & 5, and Olkaria V. In addition to the Power Stations, KenGen own fifteen wellheads generation plants one at Eburru and fourteen at Olkaria.
The Geothermal Power Plants have a combined generation capacity of 699 MW.

Olkaria I Power Station

KenGen’s Geothermal Power Plants

Olkaria I Power Station was the first geothermal power plant in Africa. The 45 MW plant was commissioned in three phases and has three units each generating 15MW of electricity. The first unit was commissioned in June 1981, the second and third units in November 1982 and March 1985, respectively.

A total of 33 wells were drilled for the station. Thirty-one of these are currently connected to the power station while two of these are retired. One of which is currently being used for hot re-injection. The turbines are direct condensing 4-stage running with an inlet steam pressure of 5 bars at temperatures of 152oC and steam consumption of 9.2 t/h/MW. The plant has had an average availability factor of over 95 percent from commissioning. The power generated is connected to the national grid via a 132KV-transmission line.
control
Control room

Olkaria II Power Station
Located in the North-Eastern sector of the greater Olkaria Geothermal field and commissioned in 2003, Olkaria II Power Station generates 105 MW. Initially, the power plant generated 70 MW from two units of 35 MW each. Later a third 35 MW unit was added. Construction of the third unit commenced in 2009 and was completed in May 2010, bringing the total generation capacity to 105 MW.

Wells were drilled between 1986 and 1993 but construction of the power plant was delayed until the year 2000 when funds became available. The project was co-financed by the World Bank, the European Investment Bank, KfW of Germany, and KenGen. Designed and constructed with the advantage of newer technology, this state-of-the-art plant is highly efficient in steam utilization. It works on a single flash plant cycle with a steam consumption of 7.5 t/h/MW. The turbines are single flow six-stage condensing with a direct contact spray jet condenser.
The power generated is transmitted to the national grid via a 220 KV double circuit line.

olkaria2a

Olkaria II Power Plant

Olkaria I Unit 4 & 5 and Olkaria IV Power Stations
Olkaria IV and Olkaria I unit 4 & 5 each generating 140 MW were commissioned in December 2014 and February 2015 respectively. This is the country’s largest Geothermal Power Project. Olkaria I unit 4 & 5 is located at Olkaria East of the Olkaria geothermal field whereas Olkaria IV is at the Olkaria domes field. The projects were funded by KenGen and bilateral partners such as World Bank, Japan International Cooperation Agency (JICA), European Investment Agency (EIB), Africa Development Bank and KfW.

olkaria456

Olkaria V Power Station
Construction of the plant which is located in the North East of the field began in January 2017. H-Young Company (HY), Mitsubishi Corporation with its compatriot Mitsubishi Hitachi Power Systems were contracted to provide some of the parts needed to equip the steam plant.
The plant features two units with a capacity of 82.7 MW each with a total of 165.4 MW. The plant will be supplied by around 500 tonnes of dry steam per hour at temperatures of about 270 centigrades. The project is being funded by a loan from the Japan International Cooperation Agency (JICA).
KenGen Successfully synchronized the first unit to the national grid on Friday 26th July. The unit achieved the design full load of 86.6 MW which is above the rated capacity of 82.7 MW.
KenGen is gearing up to commission the Olkaria V geothermal Power Plant.

Olkaria Wellhead Generation Plants
The Company has installed fourteen wellhead generating units with a capacity of 81MW in the Olkaria Geothermal field. A pilot wellhead generating unit was commissioned in February 2012. The unit is installed at well OW-37A, which is located within the Olkaria East geothermal field.
 power olkariawelhead
Olkaria Wellhead Pilot Plant

Eburru Wellhead Generation Plant
The Company engaged a consultant and contractor for the construction of the Eburru Wellhead plant that has a generation capability of 2.44 MW. The plant will be upgraded to 25 MW. The Eburru geothermal field is estimated to have a potential of more than 50MW.

eburu
Eburru Wellhead

Via Source